PROJECT DESCRIPTION 

With the construction of offshore wind farms, there is a great demand for high capacity cables to hook-up wind turbines to the shore. Dutch cable manufacturer B.V. Twentsche Kabelfabriek (TKF) produces these power cables. To meet the current high demand, they are constructing a new factory in Eemshaven. De Kok Staalbouw is a proud partner to be responsible for the construction.

De Kok Staalbouw is responsible for the design, production, delivery and assembly of the entire steel structure of the factory. This includes approximately 3,000 tonnes of steel. In this case our design scope also included design calculations of the main steel, roof, cladding and facade on top of the usual detail calculations.

The hall will be completed first, in September 2023. This hall will subsequently house various platforms, cable supports and other process-related structures.

With this new production facility, TKF expects to be able to produce up to 1,200 km of cable per year.

Facts and figures:

  • 3.500 tonnes of steel
  • 22 Trusses (30 x 8 m á 30 tonnes) 
  • approx. 14.250 squared meters facade cladding
  • approx. 24.200 squared meters roof cladding
  • 150 pieces of floor panels 

Client

B.V. Twentsche Kabelfabriek

Location

Eemshaven, the Netherlands

Delivery

June 2024

Project in focus

5 twentsche kabelfabriek eemshaven projecten kokstaalbouw
1 twentsche kabelfabriek eemshaven projecten kokstaalbouw
2 twentsche kabelfabriek eemshaven projecten kokstaalbouw
3 twentsche kabelfabriek eemshaven projecten kokstaalbouw
4 twentsche kabelfabriek eemshaven projecten kokstaalbouw
TKF2
20230504 084540
Kraan photoshop
Foto LinkedIN 05 04 2023

Deze website maakt gebruik van cookies

Deze website gebruikt cookies. Door gebruik te maken van deze website, geef je aan akkoord te zijn met het gebruik van cookies. Lees meer

Sluiten